True North Copper Limited (ASX:TNC) has released a Pre-Feasibility Study (PFS) for its Cloncurry Copper Project (CCP) in Northwest Queensland, disclosing a post-tax NPV8 of A$123M in the base case and A$165M at spot prices, alongside an Ore Reserve of 3.5 Mt at 0.86% Cu and 0.24 g/t Au, equivalent to 1.10% CuEq, containing approximately 39 kt CuEq estimated at US$4.80/lb.

Key Points

  • Post-tax NPV8 of A$123M (base case) and A$165M at spot prices; IRR of 108% and 141% respectively
  • Ore Reserve of 3.5 Mt at 0.86% Cu and 0.24 g/t Au (1.10% CuEq), containing approximately 39 kt CuEq at US$4.80/lb
  • Four-year sulphide-focused open-pit production target of approximately 50 kt CuEq, with annual production of approximately 11 kt CuEq in the first three years
  • Pre-production capital of A$8M plus A$45M working capital, with payback of 8 to 10 months; 7 months from FID to commercial production, subject to approvals and funding

PFS Financial Outcomes and Capital Requirements

The PFS outlines EBITDA of A$220M in the base case and A$269M at spot prices, with free cash flow post-tax of A$160M and A$210M respectively. Pre-production capital is disclosed at A$8M, with A$45M in working capital required. The all-in sustaining cost (AISC) is A$5.09/lb in the base case and A$5.10/lb at spot prices. The project targets 7 months from a final investment decision (FID) to commercial production, subject to approvals and funding. The payback period is 10 months in the base case and 8 months at spot prices. Spot prices referenced are as of 16 November 2026.

Ore Reserve and Mine Plan Details

The Ore Reserve of 3.5 Mt at 0.86% Cu and 0.24 g/t Au (1.10% CuEq), containing approximately 39 kt CuEq, was compiled and reviewed by Matthew Varvari, a full-time employee of True North Copper and a Fellow of the Australian Institute of Mining and Metallurgy. The PFS mine plan incorporates approximately 5 Mt of the approximately 20 Mt in total Mineral Resources. The Mongoose-Taipan portion is partially subject to the Carpentaria Joint Venture (CJV), in which TNC currently holds approximately a 36% interest, with the balance held by Glencore. The CJV accounts for approximately 16% of total contained metal in the CCP, with the non-TNC share of total approximately 10.5%. The financial evaluation has not been adjusted for these ownership interests.

Disclosed Next Steps and Development Timeline

According to the filing, TNC has outlined a staged development schedule following PFS completion. Resource extension drilling at Wallace North, Mongoose-Taipan and across the broader CCP is targeted from Q4 2026 to Q2 2027. Development optimisation, including Wynberg metallurgical test work and mine planning, is scheduled for H1 2027. Environmental approvals, including the Mongoose Mining Lease grant, are to be advanced from Q4 2026 through Q3–Q4 2027. A target FID is set for Q4 2027 to Q1 2028, subject to approvals and funding. The company disclosed it is evaluating regional toll-processing arrangements and broader strategic and commercial opportunities.