Rimfire Pacific Mining (ASX:RIM) presented its AGM update on 26 November 2026, disclosing a total scandium oxide resource inventory of 16.2 kilotonnes, a cash position of A$1.7 million at the end of the September 2026 quarter, and a series of project milestones targeting the December 2026 quarter through to the March 2027 quarter.

Key Points

  • Total scandium oxide resource inventory of 16.2Kt (16.2Kt total, 12.6Kt attributable), including 11.9Kt at the Murga deposit announced on 13 April 2026
  • Cash of A$1.7 million at end of the September 2026 quarter; share price of 1.0 cent and market capitalisation of approximately A$30 million as at 19 October 2026
  • Murga metallurgical bottle roll tests recorded recoveries of 37.1% (saprolite) and 18.4% (laterite) at 21 weeks, with 52-week projected recoveries of 73% (saprolite) and 34% (laterite)
  • Rosehill (Malamute) 2,500-metre air core drilling program scheduled to commence January 2027, with a maiden mineral resource estimate to follow
  • Bogan River licence grant expected in the late December 2026 quarter, with initial assessment of anomalies targeted for the March 2027 quarter

Murga Scandium Deposit Metallurgy and Resource Details

The Murga deposit holds an 11.9Kt scandium oxide resource as announced on 13 April 2026. According to the filing, Murga's host rock contains approximately 16% iron compared with approximately 34% iron at Rio Tinto's Burra deposit, which the company said points to simpler leaching. Bottle roll test work at 21 weeks returned recoveries of 37.1% for saprolite and 18.4% for laterite, with low acid consumption and a high scandium-to-iron ratio in saprolite noted. Column leach and agitated tank leach test work is being conducted to supplement the bottle roll data. A metallurgical study is evaluating scandium extraction via atmospheric leaching techniques, with final results targeted for the March 2027 quarter.

Project Portfolio and Upcoming Work Programs

Rimfire holds interests across several scandium-prospective projects in central New South Wales. The Fifield earn-in project, where GPR is earning a 50.1% interest, is the subject of the Murga metallurgical study. The Avondale joint venture, in which Rimfire holds 60% and GPR 40%, has seismic work targeting regional target generation in the December 2026 quarter. The Rabbit Trap project, 100% owned by Rimfire, is subject to air core drilling to underpin a maiden mineral resource estimate in the March 2027 quarter. The Bogan River project, also 100% Rimfire-owned, is adjacent to the Nyngan deposit and has multiple undrilled magnetic anomalies, with its licence grant expected in the late December 2026 quarter.

Scheduled Catalysts and Company Overview

The filing outlines a sequence of disclosed milestones. In December 2026, the company targets a long-term bottle roll recovery update along with column leach and agitated tank leach updates, a Rabbit Trap drilling update, and the Bogan River licence grant. In January 2027, details of the Rosehill (Malamute) air core drilling program and a proposed Bogan River work program are targeted. For the March 2027 quarter, the company targets Rosehill drilling results to underpin a maiden mineral resource estimate, final metallurgical study results, and commencement of Bogan River exploration. A Murga desktop financial study is also listed as a later milestone. The board comprises Bronwyn Barnes as Executive Chair, David Hutton as Technical Director, Ian McCubbing and Andrew Knox as Non-Executive Directors, with Dr Peter Crowhurst as Exploration Manager and Greg Keane as Chief Financial Officer.