Element 25 Limited (ASX:E25) presented an overview of its Butcherbird Manganese Project expansion and global high-purity manganese sulphate monohydrate (HPMSM) strategy at the IMARC Conference in October 2026, disclosing that early works at the Western Australian mine site are materially complete and the project has moved into physical execution ahead of a targeted Q1 2027 completion.
Key Points
- Early works package at Butcherbird is materially complete, with site clearing, bulk earthworks, process water pond commissioning and administration facilities relocation delivered.
- All major equipment packages have been awarded, ordered and are in manufacture, with detailed engineering and IFC packages materially complete across CSMPE&I disciplines.
- The Butcherbird expansion targets production of 1.1 million tonnes per annum of manganese concentrate at a grade of 31.6% Mn, with a mine life of 18.3 years.
- The project has a post-tax NPV8 (real) of AUD $379 million, a pre-tax IRR of 96%, and a capital cost of AUD $64.8 million, according to the company's feasibility study.
- Element 25 has 326 million issued shares and carries nil total debt, according to the filing.
Butcherbird Expansion Delivery Status
According to the filing, the Butcherbird Manganese Project expansion has progressed across three workstreams: early works, process plant award, and operational readiness. Early site works delivered include site clearing, grubbing and bulk earthworks, commissioning of a new process water pond with pumping and pipelines, relocation of administration facilities, and establishment of power, communications, potable water, wastewater, roads and drainage. Mining, ore haulage, engineering, offtake and Kumarina camp agreements are disclosed as complete. The NAIF contractual close process is described as approaching completion.
Butcherbird Mineral Resource and Reserve
The filing states the Butcherbird Manganese Project holds a mineral resource of 274 million tonnes at 10.0% Mn, containing 27.4 million tonnes of manganese. The mining reserve stands at 101.4 million tonnes at 10.4% Mn, containing 10.5 million tonnes of manganese. The project holds a granted mining lease and is described as fully permitted. The filing notes the ore is suitable for ferroalloys, battery-grade HPMSM and electrolytic manganese metal. Operations are described as requiring no explosives, no dewatering, and one reagent — water.
Louisiana HPMSM Facility and Global Expansion Plans
The filing discloses that Element 25's strategic vision includes constructing a first US HPMSM processing facility in Louisiana, producing 65,000 tonnes per annum of battery-grade HPMSM in partnership with GM and Stellantis. The company also disclosed plans for multiple HPMSM modules globally targeting Europe and Asia. The filing identifies the one-year plan as the Butcherbird expansion to 1.1 million tonnes per annum of manganese concentrate, the three-year plan as the Louisiana HPMSM facility, and the ten-year plan as further HPMSM expansion across the European Union and Asia.