Brookside Energy Limited (ASX:BRK) has disclosed that combined gross production from its Sabres and Whalers wells at the Suttles Pad in the SWISH Play, southern SCOOP, Anadarko Basin, Oklahoma, has exceeded 1,500 barrels of oil equivalent per day (BOEPD) over a 24-hour period, up from the previously reported 1,200 BOEPD milestone.

Key Points

  • Combined gross production from Sabres and Whalers wells has exceeded 1,500 BOEPD over a 24-hour period, up from the previously reported 1,200 BOEPD
  • Suttles Pad development costs continue to track approximately 15% below budget
  • Sabres (Sycamore) is producing through conventional gas lift, while Whalers (Woodford) continues to flow naturally
  • Both wells continue to clean up, with substantial volumes of completion water still being recovered
  • The company expects to report representative initial production (IP) rates once wells have progressed sufficiently through flowback

Suttles Pad Production Update

According to the filing, combined gross production from the Sabres and Whalers wells at the Suttles Pad has now exceeded 1,500 BOEPD over a 24-hour period. The liquids contribution remains within the company's forecast range. Both wells continue to clean up, with substantial volumes of completion water still being recovered. Production volumes include estimated natural gas liquids based on a yield of 120 barrels per million cubic feet of raw gas, with gas volumes adjusted for 20% shrinkage and residue gas converted to BOE at 6 Mcf per BOE.

Well Lifting Arrangements and Flowback Status

The filing states that Sabres (Sycamore) is producing through conventional gas lift, while Whalers (Woodford) continues to flow naturally. The company disclosed that these different lifting arrangements, together with the ongoing recovery of completion fluids, influence the early production profiles of the two wells. Brookside said it will continue to monitor production and well clean-up over the coming months as the production profiles develop, and expects to report representative initial production rates once the wells have progressed sufficiently through flowback to provide a more meaningful measure of their performance.

Development Costs and Budget Performance

The filing disclosed that Suttles Pad development costs continue to track approximately 15% below budget. Managing Director and CEO David Prentice commented: "Production continues to build, and with development costs tracking below budget, we're well positioned to deliver strong returns from Suttles. The real test is how quickly we recover our investment and the cash these wells generate over their producing lives. That's how we measure success, and ultimately how we create value for shareholders." The filing stated the announcement was authorised for release by the Board of Directors of Brookside Energy Limited.