Broken Hill Mines (ASX:BHM) disclosed record quarterly sales revenue of A$37.6m and milestone silver production of 102,922 ounces for the three months ending 30 September 2026, with the company also reporting total liquidity of A$112.9m including A$89.5m in cash following completion of an A$85m capital raise.
Key Points
- Record quarterly sales revenue of A$37.6m against cash operating costs of A$33.4m for the September 2026 quarter
- Silver production reached 102,922oz, described as the highest since June 2020 and the first time the company exceeded 100,000oz Ag in a single quarter
- Record quarterly ore mined of 142,523 tonnes, up 6.9% quarter-on-quarter and 20.3% year-on-year, drawn from Western Min, Main Lode and Pinnacles
- A$85m two-tranche capital raise completed, with tranche 1 (A$60m) settled during the quarter and tranche 2 (A$25m) completed in October, both at A$0.76 per share
- Maiden Exploration Target over the Centenary Zone at Rasp described as due for imminent release, following confirmation of high-grade silver, lead and zinc intersections
September 2026 Production and Financial Performance
Ore processed during the September 2026 quarter totalled 129,084 tonnes, up 8.2% from the prior quarter, with silver grade of 31.0 g/t, lead grade of 2.2% and zinc grade of 2.8%. Lead production was 2,381 tonnes and zinc production was 3,024 tonnes. In-quarter cash receipts from sales were A$20.2m, with the difference from the A$37.6m revenue figure attributed to shipment timing. Operating costs comprised production costs of A$21.8m, staff costs of A$9.4m, and administration, corporate and net interest costs of A$2.2m. Growth capital expenditure totalled A$13.3m, primarily associated with the Tailings Dewatering Plant (A$5.6m) and Pinnacles Mine restart works (A$5.4m). Sustaining capital expenditure was A$5.8m.
Centenary Zone Discovery and Exploration Intersections
The filing disclosed confirmation of a bulk tonnage ore body discovery within the Centenary Zone at Rasp, with intersections including 25.8m at 11.7% ZnEq and 323g/t AgEq from 415m, and 17.8m at 10.1% ZnEq and 280g/t AgEq from 420m. A sub-interval of 5.4m at 19.5% ZnEq and 540g/t AgEq from 432m was also reported. At Pinnacles, further high-grade intersections within the open pit area included 14.4m at 20.3% ZnEq and 561g/t AgEq from 69.3m, along with gold and copper results including 5.6m at 3.2g/t Au and 0.2% Cu from 87.0m. The company stated a maiden Exploration Target over the Centenary Zone is due for imminent release.
Corporate Developments and Balance Sheet Position
Broken Hill Mines completed the A$85m capital raise at A$0.76 per share across two tranches, with proceeds planned to be applied to a Centenary production decline, accelerated resource drilling, infrastructure upgrades, and Pinnacles production growth and resource drilling. The company reduced debt by A$8.9m, described as a 17% reduction, with approximately A$19.0m available under its revolving credit facility. A non-binding Letter of Intent was signed with zinc offtake partner Ausinmet Pte Ltd for expanded offtake and a US$30m financing facility. The Rasp Tailings Dewatering Plant remains on budget and schedule for availability in the first half of calendar year 2027.