Blackstone Minerals (ASX:BSX) has reported a cash and cash equivalents position of $12.2M at the end of the September 2026 quarter, down from $13.7M at the end of the prior period, with net cash spent during the period of $1.6M, according to the company's quarterly activities report and Appendix 5B for the period ending 30 September 2026.
Key Points
- Cash and cash equivalents of $12.2M at 30 September 2026, with net cash spent of $1.6M during the quarter
- Listed investments of approximately $700K at end of quarter
- Pre-Feasibility Study (PFS) activities progressed at the Mankayan Copper-Gold-Silver Project in the Philippines, with completion scheduled within FY27
- Mankayan JORC 2012 Mineral Resource stands at 793Mt at 0.65% CuEq, containing 2.8Mt Cu, 9.7Moz Au and 20.4Moz Ag
- Transfer documentation for Stage 1 of the binding strategic agreement for Ta Khoa Nickel executed, with completion subject to Vietnamese government registration
Mankayan Pre-Feasibility Study Activities
PFS activities at the Mankayan Copper-Gold-Silver Project in the Philippines continued during the September 2026 quarter following the appointment of four key consultants and engineering groups in June 2026. Lycopodium (APAC) Pty Ltd is responsible for metallurgy, process plant design and PFS study management, with metallurgical test work continuing at ALS Metallurgy Pty Ltd under the guidance of Pitch Black Group Pty Ltd. Mining Plus Pty Ltd identified two of seven potential mining methods as optimum for the size of the resources — sub level caving potentially leading to a block cave — and did not identify any material concerns, red flags or fatal flaws in the 2020 JORC 2012 Resource Model. Derisk Geomining Consultants are generating a resource block model suitable for mine planning.
Mankayan Mineral Resource and Community Engagement
The Mankayan Project's JORC 2012 Mineral Resource is reported at a cut-off criterion of 0.25% CuEq as at 30 September 2020. The Indicated resource totals 638Mt at 0.68% CuEq, containing 2.3Mt Cu, 8.2Moz Au and 18Moz Ag. The Inferred resource totals 155Mt at 0.52% CuEq, containing 0.5Mt Cu, 1.5Moz Au and 2.4Moz Ag. GHD Pty Ltd is responsible for infrastructure, the tailings storage facility and socio-environmental aspects, with activities in that area paused post-quarter. CMDC has continued engagement with the Municipal Mayor, community members and Regional and National Government bodies. No activities were recorded at the Gold Bridge project in Canada during the quarter.
Ta Khoa Nickel Project Transfer and Vietnam Update
Blackstone and Xuan Loc Tho Co. Ltd executed transfer documentation for Stage 1 of the binding strategic agreement, under which a 55% interest in Ban Phuc Nickel Mine (BPNM) will be transferred to Xuan Loc Tho. Completion of the transfer remains subject to processing and registration by relevant Vietnamese government authorities, which had not occurred as at the date of the report. On completion, Blackstone will retain a 44.64% interest in BPNM and will be carried through to the granting of a construction license for the Ta Khoa Nickel Project. The investment policy dossier for the Ta Khoa Refinery remains on hold until an Industrial Cluster license is issued. The company disclosed it continues to achieve a zero-holding cost outcome for Vietnam.