Black Rock Mining (ASX:BKT) has released its third annual Sustainability Report for the financial year ended 30 June 2026, outlining environmental, social and governance activities related to the Mahenge Graphite Project in Tanzania, including the commencement of the Early Works Program and progress on community compensation and biodiversity planning.
Key Points
- The FY26 Sustainability Report covers Black Rock Mining Limited and its Tanzanian subsidiary Faru Graphite Corporation Limited.
- The Mahenge Graphite Project holds a JORC-compliant resource of 213 million tonnes at 7.8% TGC and a reserve of 70 million tonnes at 8.5% TGC.
- The Early Works Program commenced during the financial year ended 30 June 2026.
- The Project is forecast to be positioned in the first quartile of the global graphite cost curve, according to the updated enhanced Definitive Feasibility Study released on 10 October 2022.
- The report is a voluntary disclosure and does not constitute the statutory Sustainability Report under Chapter 2M of the Corporations Act 2001.
Mahenge Graphite Project Location and Resource Base
The Mahenge Graphite Project is located in south-eastern Tanzania, in the Ulanga District of the Morogoro Region, approximately 350 kilometres southwest of Dar es Salaam and 70 kilometres south of the town of Ifakara. The project is described as one of the largest JORC-compliant flake graphite resources globally, hosting a resource of 213 million tonnes at 7.8% total graphitic carbon and a reserve of 70 million tonnes at 8.5% total graphitic carbon. Black Rock Mining holds the project through its Tanzanian subsidiary, Faru Graphite Corporation Limited.
Project Competitive Advantages and Cost Positioning
Industry benchmarking from the updated enhanced Definitive Feasibility Study indicates the project is forecast to sit in the first quartile of the global graphite cost curve. The filing attributes this positioning to a very low life-of-mine strip ratio of 0.77, access to competitively priced hydro-dominated grid power, and a product mix with a relatively high proportion of large-flake products. The project is to be connected to Tanzania's grid through a new 220kV transmission line from Ifakara. The company also holds a strategic alliance with POSCO, a South Korean-based battery materials company.
FY26 Sustainability Milestones and Reporting Scope
During FY26, the company disclosed milestones including commencement of the Early Works Program, continued engagement with the Government of Tanzania, progress on biodiversity planning, implementation of community compensation and livelihood restoration programs, and ongoing development of its sustainability framework. The report covers governance, strategy, performance and key initiatives across environmental, social and governance categories. Black Rock Mining stated it does not currently meet the criteria for mandatory Australian Sustainability Reporting Standards reporting and that its reporting obligations will be assessed as operations progress.