Aspire Mining Limited (ASX:AKM) has reported that subsidiary Khurgatai Khairkhan LLC raised US$11.2 million across ten tranches of the Ovoot Bond program as at 28 October 2026, as the company advanced site establishment at the Coal Handling and Processing Plant (CHPP) and confirmed a Total Coal Reserve of 130.1 Mt for its Ovoot Coking Coal Project in Mongolia.
Key Points
- US$11.2 million raised across ten Ovoot Bond tranches as at 28 October 2026, with fixed coupons ranging from 11.0% to 13.0% p.a. and terms of between 12 and 36 months
- Updated Coal Reserve estimate reconfirmed Total Coal Reserve of 130.1 Mt and Marketable Coal Reserve of 97.9 Mt, effective 31 March 2026
- Phase 1 pre-production capital expenditure forecast at approximately US$61.2 million; economic evaluation returns a post-tax NPV10 of US$1,483.3 million and post-tax real IRR of approximately 60%
- Gobi Infrastructure Partners LLC mobilised to the CHPP site, establishing a contractor's camp and commissioning a concrete batching plant
- Mr Chen Li appointed as Independent Non-Executive Director on 24 August 2026
Ovoot Bond Program Launch and Capital Raised
The Mongolian Association of Securities Dealers Registration Committee approved registration of the Ovoot Bond program for an aggregate principal amount of up to US$60.0 million on 27 July 2026, and the Bank of Mongolia granted permission on 6 August 2026 for the issue and related payments to be transacted in US dollars. Tenger Capital Securities LLC is the underwriter. As at 28 October 2026, Khurgatai Khairkhan LLC had raised US$11.2 million across ten tranches, with coupons payable quarterly and principal due at maturity. KK's obligations are supported by guarantees from Aspire's largest shareholder, Mr Tserenpuntsag Tsedendamba, and Gemnet LLC, with no guarantee fee payable by Aspire or KK.
Updated Coal Reserve Estimate and Economic Evaluation
On 11 September 2026, Aspire released an updated Coal Reserve estimate for the Ovoot Coking Coal Project prepared by Glogex Consulting LLC in accordance with the JORC Code (2012), effective 31 March 2026. The estimate reconfirmed a Total Coal Reserve of 130.1 Mt, comprising 76.8 Mt Proved and 53.3 Mt Probable, and a Marketable Coal Reserve of 97.9 Mt, comprising 60.0 Mt Proved and 37.9 Mt Probable. The updated Project Cost Model forecasts Phase 1 pre-production capital expenditure of approximately US$61.2 million, excluding approximately US$24.6 million of estimated working capital and capital expenditure incurred to 31 December 2025, based on an assumed long-term coking coal price of US$230 per tonne DDP Erlian, China.
CHPP Site Establishment and Highway Project Progress
During the quarter, Gobi Infrastructure Partners LLC, the main construction subcontractor beneath CCTEG-IEC, mobilised to the CHPP site, establishing the contractor's camp and commissioning a concrete batching plant. Regarding the Murun–Uliastai Highway Project, final reviews of the PPP Agreement were performed by the Ministry of Economy and Development, the Ministry of Finance, and the Ministry of Road and Transport, with approval pending from the cabinet of the Government of Mongolia. Aspire held cash of approximately US$2.1 million at the end of the quarter ending 30 September 2026.